CORSIA Validation / Verification Process

4 Main Stages

Activities

Deliverables by TÜV SÜD PSB

Timeline (proposed – to be confirmed and agreed upon with client)

Pre-engagement assessment

Contract review and appointment as verifier.

Appointment /engagement letter with client

By July of the reporting year

Verification Planning

Conduct strategic analysis & risk assessment of the facility’s operations & GHG document & data. Develop & review verification summary plan.

-

By Sept of the reporting year

Conducting Verification

Perform preliminary detailed verification based on emission report. Perform data checks, evaluate rules & principles, check systems and QA/QC control. Raise action list related to misstatements and non-conformities, and revise verification plan summary, if required.

Action List (Preliminary)

Within fifteen (15) days of the start of engagement or receiving of partial supporting documents, whichever is later

Perform on-site verification to perform year-end re-conciliation, check compliance and assess the GHG assertions. Raise action list related to misstatements and non-conformities, and revise verification plan summary, if required.

Site Visit Plan & Action List

By Jan to Mar after reporting year

Submission of corrective action by clients for issues raised; Follow up on actions taken by client to address misstatements and non-conformities.

Action list

By Jan to Mar after reporting year

Verification Reporting

Prepare, independent review & issue verification report to client

Verification Report (Client Copy)

By Mar after the reporting year

Authorization consent for release of verified emission report to States

Authorization Form (Client Copy)

By Mar after the reporting year

Submit verification report along with emissions report and/or emission cancellation report to States

(States Copy)

Deadlines: Before 31 Apr after the reporting year


GHG Validation / Verification Process

4 Main Stages

Activities

Deliverables by TÜV SÜD PSB

Timeline (proposed – to be confirmed and agreed upon with client)

Pre-engagement assessment

Contract review and appointment as verifier.

Appointment / engagement letter

NA

Verification Planning

Conduct strategic analysis & risk assessment of the facility’s operations & GHG document & data. Develop & review verification summary plan.

-

Within fifteen (15) days of the start of engagement or receiving of partial supporting documents, whichever is later 

Conducting Verification activities

Perform preliminary detailed verification based on emission report. Perform data checks, evaluate rules & principles, check systems and QA/QC control. Raise action list related to misstatements and non-conformities, and revise verification plan summary, if required.

Action List (Preliminary) 

Within fifteen (15) days of the start of engagement or receiving of partial supporting documents, whichever is later.

Conduct on-site visit check compliance and assess the GHG assertions. Perform materiality check & final check on Emission Report & investigate any anomalies. Raise action list related to misstatements and non-conformities, and revise verification plan summary, if required.

Action List (Site)

Within one (1) month of the start of a verification engagement or receiving of a full set of supporting documents, whichever is later.

Submission of corrective action by clients for issues raised; Follow up on actions taken by client to address misstatements and non-conformities.

Action List (Final) with corrective action

Within one (1) month after site visit (delay of response is excluded).

Verification Reporting Pre-engagement assessment 

Prepare, independent review & issue verification report / statement to client

Verification Report & Verification Statement

Within fifteen (15) days after closure of all corrective actions.


 

NEA Carbon Reduction Programme

4 Main Stages

Activities

Deliverables by TÜV SÜD PSB

Timeline (proposed – to be confirmed and agreed upon with client)

Pre-engagement assessment

Contract review and appointment as verifier.

Appointment / engagement letter

NA

Verification Planning

Conduct strategic analysis & risk assessment of the facility’s operations & GHG document & data. Develop & review verification summary plan.

-

Within fifteen (15) days of the start of engagement or receiving of partial supporting documents, whichever is later

Conducting Verification activities

Perform preliminary detailed verification based on emission report. Perform data checks, evaluate rules & principles, check systems and QA/QC control. Raise action list related to misstatements and non-conformities, and revise verification plan summary, if required.

Action List (Preliminary)

Within fifteen (15) days of the start of engagement or receiving of partial supporting documents, whichever is later.

Conduct on-site visit check compliance and assess the GHG assertions. Perform materiality check & final check on Emission Report & investigate any anomalies. Raise action list related to misstatements and non-conformities, and revise verification plan summary, if required.

Action List (Site)

Within one (1) month of the start of a verification engagement or receiving of a full set of supporting documents, whichever is later.

Submission of corrective action by clients for issues raised; Follow up on actions taken by client to address misstatements and non-conformities.

Action List (Final) with corrective action

Within one (1) month after site visit (delay of response is excluded).

Verification Reporting Pre-engagement assessment

Prepare, independent review & issue verification report / statement to client

Verification Report & Verification Statement

Within fifteen (15) days after closure of all corrective actions.